All four locations: Kipling, Hawthorne, Garrott, and Emerson have completed their underground work, paving for pavement, sidewalks, and driveways, as well as landscaping and sod installation, with a 100% completion rate.
Audubon:
Underground – 100% Complete
Paving (Pavement/Sidewalks/Driveways) - 100% Complete
Landscaping/Sod – 85% Complete – Anticipated Completion March 2024
Holman:
Underground – 50% Complete – Anticipated Completion September 2024
Paving (Pavement/Sidewalks/Driveways) - 0% Complete - Anticipated Completion October 2024
Landscaping/Sod – 0% Complete – Anticipates Completion October 2024
Fannin:
Underground – 80% Complete - Anticipated Completion September 2024
Paving (Pavement/Sidewalks/Driveways) – 80% Complete - Anticipated Completion October 2024
Landscaping/Sod – 30% Complete - Anticipates Completion October 2024
Tuam:
Underground – 60% Complete (Large Diameter Water Line) – Anticipated Completion August 2024
Paving (Pavement/Sidewalks/Driveways) - 15% Complete – Anticipated Completion September 2024
Landscaping/Sod – 0% Complete – Anticipated Completion September 2024