All four locations: Kipling, Hawthorne, Garrott, and Emerson have completed their underground work, paving for pavement, sidewalks, and driveways, as well as landscaping and sod installation, with a 100% completion rate.


Audubon:

Underground – 100% Complete

Paving (Pavement/Sidewalks/Driveways) - 100% Complete

Landscaping/Sod – 85% Complete – Anticipated Completion March 2024


Holman:

Underground – 50% Complete – Anticipated Completion September 2024

Paving (Pavement/Sidewalks/Driveways) - 0% Complete - Anticipated Completion October 2024

Landscaping/Sod – 0% Complete – Anticipates Completion October 2024


Fannin:

Underground – 80% Complete - Anticipated Completion September 2024

Paving (Pavement/Sidewalks/Driveways) – 80% Complete - Anticipated Completion October 2024

Landscaping/Sod – 30% Complete - Anticipates Completion October 2024


Tuam:

Underground – 60% Complete (Large Diameter Water Line) – Anticipated Completion August 2024

Paving (Pavement/Sidewalks/Driveways) - 15% Complete – Anticipated Completion September 2024

Landscaping/Sod – 0% Complete – Anticipated Completion September 2024