PROJECT NUMBER R-000267-0128
LOCATION Along Brompton and Kirby Drive between Bradford (North) and Ayershire (South)
DETAILS The project provides the rehabilitation of Ayershire, Brompton, Bradford, Kirby No. 2 lift stations by upgrading their mechanical, structural, and instrumentation systems, as well as site work.
MAP
What is the purpose of this project?
This project will rehabilitate four existing sanitary sewer lift stations to allow for continued function and upgrade to current standards. The project will also increase the capacity of one lift station to accommodate projected increase in future wastewater flows.
How long is this project going to take to complete?
16 months (480 calendar days). Work is scheduled to begin August 2020 and anticipated to be completed in December 2021. The project schedule depends upon weather conditions.
DETAILS The project provides the rehabilitation of Ayershire, Brompton, Bradford, Kirby No. 2 lift stations by upgrading their mechanical, structural, and instrumentation systems, as well as site work.
MAP
What is the purpose of this project?
This project will rehabilitate four existing sanitary sewer lift stations to allow for continued function and upgrade to current standards. The project will also increase the capacity of one lift station to accommodate projected increase in future wastewater flows.
How long is this project going to take to complete?
16 months (480 calendar days). Work is scheduled to begin August 2020 and anticipated to be completed in December 2021. The project schedule depends upon weather conditions.