PROJECT NUMBER S-000900-0131
LOCATION 72-Inch Water Line from Emancipation to Tuam
BUDGET $48.7 Million
TYPE Water Line
START Winter 2020
COMPLETION Summer 2022
DETAILS The project provides for the following upgrades: waterlines, sanitary and storm systems, new concrete pavements.
MAP
General Project Information
What is the purpose of this project? The 72-Inch water transmission main will carry portable water to the City’s Southwest Pump Station to increase the overall capacity in the region's drinking water. | |
How long is this project going to take to complete? 24 months (720 calendar days). Work is scheduled to begin in early Winter 2020 and is anticipated to be completed in Summer 2022. The project schedule depends upon weather conditions. |
Have More Questions? Click here for more answers