The project is approximately 5% complete. The contractor has mobilized sites and begun underground construction at the intersection of Sabo Rd. and Beltway 8. The contractor is also working on underground construction at Sageglen Drive and Sagedowne Lane. The targeted completion date for the project is Spring 2025.