The work on Bellaire and Hillcroft site has been completed, and the new line is back in service. Only one site remains under this project, which pertains to a 42-inch Water Line at Hunting Bayou at IH-10. The contractor is currently tunneling a 60-inch steel casing and will finish the installation of the 60-inch steel casing by Friday, 4, 2023. From August 7 to August 18 Contractor is scheduled to install the 42-inch Water Line. Then from August 21st to September 22, the Contractor is scheduled to perform disinfection of the 42-inch waterline and perform all connections to the existing waterline. After this, Contractor will restore the site and complete this site by October 13, 2023. Please let me know if you have any questions or need additional information. Thanks