Latest News

The project is progressing well. Stormwater installation is complete on Gloria, Wynnewood, and Pandora, and is currently underway along Evangeline. Pavement installation has been completed on Gloria and has now commenced on both Wynnewood and Pandora. We’re pleased to report that the project remains on schedule for completion by Winter 2026. Thank you for your continued support—stay tuned for more updates as progress continues!

Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link
#<Object:0x00000000546d1b78>