Westridge Regional Lift Station

Share Westridge Regional Lift Station on Facebook Share Westridge Regional Lift Station on Twitter Share Westridge Regional Lift Station on Linkedin Email Westridge Regional Lift Station link

PROJECT NUMBER R-000267-128A-4

LOCATION Refer to Project Map

COUNCIL DISTRICT K

BUDGET $36,104,000

TYPE Wastewater

START Winter 2024

COMPLETION Winter 2025

DETAILS Work of the Contract is for the construction of the Westridge Regional Lift Station and Force Main, construction of gravity sanitary sewer lines, installation and operation of diversion pumping, abandonment and demolition of three existing Lift Stations (Kirby No.1, West Westridge, and Main Street), and site restoration.


MAP

Project Map


General Project Information

What is the purpose of this project?
This project is part of the City’s Capital Improvement Plan (CIP) Consolidation Package for wastewater facilities.

How long is this project going to take to complete?
21 months (640 calendar days). Work is scheduled to begin in Winter 2024 and is anticipated to be completed in Winter 2025. The project schedule depends upon weather conditions. Please see the phasing map for details.


Have More Questions? Click here for more answers

PROJECT NUMBER R-000267-128A-4

LOCATION Refer to Project Map

COUNCIL DISTRICT K

BUDGET $36,104,000

TYPE Wastewater

START Winter 2024

COMPLETION Winter 2025

DETAILS Work of the Contract is for the construction of the Westridge Regional Lift Station and Force Main, construction of gravity sanitary sewer lines, installation and operation of diversion pumping, abandonment and demolition of three existing Lift Stations (Kirby No.1, West Westridge, and Main Street), and site restoration.


MAP

Project Map


General Project Information

What is the purpose of this project?
This project is part of the City’s Capital Improvement Plan (CIP) Consolidation Package for wastewater facilities.

How long is this project going to take to complete?
21 months (640 calendar days). Work is scheduled to begin in Winter 2024 and is anticipated to be completed in Winter 2025. The project schedule depends upon weather conditions. Please see the phasing map for details.


Have More Questions? Click here for more answers

  • Latest Update

    Share Latest Update on Facebook Share Latest Update on Twitter Share Latest Update on Linkedin Email Latest Update link

    The project is approximately 45% complete. The gravity wastewater line is approximately 68% complete, and the force main wastewater line is approximately 53% complete. Anticipate major traffic switch along Buffalo Speedway, two-way traffic, one lane in each direction, from Murworth to Fairhope, beginning Winter 2024. The targeted completion date for the project is Winter 2025.

  • Reduced Lanes, Expect Delays

    Share Reduced Lanes, Expect Delays on Facebook Share Reduced Lanes, Expect Delays on Twitter Share Reduced Lanes, Expect Delays on Linkedin Email Reduced Lanes, Expect Delays link

    Reduced Lanes, Expect Delays

  • April 2023 Update

    Share April 2023 Update on Facebook Share April 2023 Update on Twitter Share April 2023 Update on Linkedin Email April 2023 Update link

    The project is approximately 5% completed in place. Major construction activities include constructing tunnel shafts along Main Street and Murworth.

Page last updated: 03 Apr 2024, 11:55 AM