Westheimer Water Line Project

Share Westheimer Water Line Project on Facebook Share Westheimer Water Line Project on Twitter Share Westheimer Water Line Project on Linkedin Email Westheimer Water Line Project link

Project Overview

Council District: C,G







Project Impact Area




Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

Project Overview

Council District: C,G







Project Impact Area




Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The Westheimer Paving Project is progressing well.

    Segment 3: Weslayan to Timmons

    Water line installation is complete. METRO is scheduled to perform milling and overlay operations for Segments 3 and 4 simultaneously.

    Segment 4: Timmons to Buffalo Speedway

    Water line installation is also complete. Roadway repairs are underway this week and are expected to continue into next week, weather permitting. Once repairs are finalized, METRO will proceed with milling and overlay work.

    We appreciate your continued patience and support as we work to improve the roadway infrastructure. Stay tuned for more updates!

    The Westheimer Paving Project is progressing well.

    Segment 3: Weslayan to Timmons

    Water line installation is complete. METRO is scheduled to perform milling and overlay operations for Segments 3 and 4 simultaneously.

    Segment 4: Timmons to Buffalo Speedway

    Water line installation is also complete. Roadway repairs are underway this week and are expected to continue into next week, weather permitting. Once repairs are finalized, METRO will proceed with milling and overlay work.

    We appreciate your continued patience and support as we work to improve the roadway infrastructure. Stay tuned for more updates!

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    We are happy to announce! The construction of the water line for Segment 3 is set to start on July 24, 2024.

    We are happy to announce! The construction of the water line for Segment 3 is set to start on July 24, 2024.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Great News! Construction of the wastewater line for Segment 1 began on July 1, 2024, and Segment 2 followed on July 17, 2024.

    Great News! Construction of the wastewater line for Segment 1 began on July 1, 2024, and Segment 2 followed on July 17, 2024.

Page last updated: 16 Jun 2025, 11:45 AM