DETAILS This project provides for the cleaning, inspection, rehabilitation and preventive maintenance of existing water storage tanks.
MAP
General Project Information
What is the purpose of this project? This project is necessary to meet the supply demand capacity, water storage capacity requirements of the TCEQ and the Annual State Inspection.
How long is this project going to take to complete? 17 months (520 calendar days). Work is scheduled to begin on Monday, October 18, 2021, and anticipated to be completed in Spring 2023. The project schedule depends upon weather conditions.
DETAILS This project provides for the cleaning, inspection, rehabilitation and preventive maintenance of existing water storage tanks.
MAP
General Project Information
What is the purpose of this project? This project is necessary to meet the supply demand capacity, water storage capacity requirements of the TCEQ and the Annual State Inspection.
How long is this project going to take to complete? 17 months (520 calendar days). Work is scheduled to begin on Monday, October 18, 2021, and anticipated to be completed in Spring 2023. The project schedule depends upon weather conditions.
Share on FacebookShare on TwitterShare on LinkedinEmail this link
All work at tank site is complete and the Contractor is working on Punchlist. The substantial completion certificate was issued, and a final completion inspection is scheduled for 4/26/23.
Share on FacebookShare on TwitterShare on LinkedinEmail this link
Currently three sites have been completed and the contractor is preparing for partial substantial completion for Sharpstown on 1/26/23. After that only one site will be remaining to complete this project. Project is on schedule for completion.