Rehabilitation of Water Storage Tanks - Package 12

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER S-000600-0052

LOCATION See project map

COUNCIL DISTRICT F, G, J & K

BUDGET $4,265,190

TYPE Water

START Fall 2021

COMPLETION Spring 2023

DETAILS This project provides for the cleaning, inspection, rehabilitation and preventive maintenance of existing water storage tanks.


MAP

Project Map



General Project Information

What is the purpose of this project? This project is necessary to meet the supply demand capacity, water storage capacity requirements of the TCEQ and the Annual State Inspection.
How long is this project going to take to complete? 17 months (520 calendar days). Work is scheduled to begin on Monday, October 18, 2021, and anticipated to be completed in Spring 2023. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

PROJECT NUMBER S-000600-0052

LOCATION See project map

COUNCIL DISTRICT F, G, J & K

BUDGET $4,265,190

TYPE Water

START Fall 2021

COMPLETION Spring 2023

DETAILS This project provides for the cleaning, inspection, rehabilitation and preventive maintenance of existing water storage tanks.


MAP

Project Map



General Project Information

What is the purpose of this project? This project is necessary to meet the supply demand capacity, water storage capacity requirements of the TCEQ and the Annual State Inspection.
How long is this project going to take to complete? 17 months (520 calendar days). Work is scheduled to begin on Monday, October 18, 2021, and anticipated to be completed in Spring 2023. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

  • April 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    All work at tank site is complete and the Contractor is working on Punchlist. The substantial completion certificate was issued, and a final completion inspection is scheduled for 4/26/23.

  • January 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Currently three sites have been completed and the contractor is preparing for partial substantial completion for Sharpstown on 1/26/23. After that only one site will be remaining to complete this project. Project is on schedule for completion.