Wastewater Force Main Renewal and Replacement Sleepy Hollow, Telephone Road #1, and West Park #1

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER R-000035-0012

LOCATION Claremont and Buffalo Speedway between Mockingbird Ln. and W. Alabama St.

COUNCIL DISTRICT C, G, I

BUDGET $12,690,060

TYPE Wastewater

START Summer 2020

COMPLETION Winter 2023

DETAILS The project consists of the abandonment of the existing lift station on Chevy Chase. The flow will be diverted to the sewer line along Claremont/Buffalo Speedway. Improvements include street repairs, drainage, paving, and storm sewer and sanitary improvements.


MAP

project map




What is the purpose of this project?
(1) The purpose of this project is to replace the aging sanitary sewer force main, divert sanitary flows with a 36-inch gravity sewer, and decommission Sleepy Hollow Lift Station. (2) Replacement installation of the force main and connecting to Telephone Rd. No. 1 lift station.
How long is this project going to take to complete?
30 months (630 calendar days). Work is scheduled to begin Tuesday, July 7, 2020, and anticipated to be completed in Winter 2023. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers



PROJECT NUMBER R-000035-0012

LOCATION Claremont and Buffalo Speedway between Mockingbird Ln. and W. Alabama St.

COUNCIL DISTRICT C, G, I

BUDGET $12,690,060

TYPE Wastewater

START Summer 2020

COMPLETION Winter 2023

DETAILS The project consists of the abandonment of the existing lift station on Chevy Chase. The flow will be diverted to the sewer line along Claremont/Buffalo Speedway. Improvements include street repairs, drainage, paving, and storm sewer and sanitary improvements.


MAP

project map




What is the purpose of this project?
(1) The purpose of this project is to replace the aging sanitary sewer force main, divert sanitary flows with a 36-inch gravity sewer, and decommission Sleepy Hollow Lift Station. (2) Replacement installation of the force main and connecting to Telephone Rd. No. 1 lift station.
How long is this project going to take to complete?
30 months (630 calendar days). Work is scheduled to begin Tuesday, July 7, 2020, and anticipated to be completed in Winter 2023. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers



Is there anything you want us to know?

You need to be signed in to add your question.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    When is the Chevy chase dr part of the sleepyhollow sewer project scheduled to be completed?

    dm4545 asked over 1 year ago

    Thank you for your question. The contractor's schedule at the Lift Station/water fountain between Chevy Chase Dr. and Sleepy Hollow Court shows that work is anticipated to begin just before Thanksgiving and the restoration of this will be completed just before Christmas.