  • Share I was told by Harris County Precinct 4 that the road construction on Park Row between Eldridge and Highway 6 is a Houston Public Works project and so I'm reaching out to you. Park Row has had traffic cones blocking lanes of traffic for over a year and it appears as though all construction is finished many months ago. Can you please provide an update on when this will be finished as it severely impacts my daily commute. Thank you. Eric on Facebook Share I was told by Harris County Precinct 4 that the road construction on Park Row between Eldridge and Highway 6 is a Houston Public Works project and so I'm reaching out to you. Park Row has had traffic cones blocking lanes of traffic for over a year and it appears as though all construction is finished many months ago. Can you please provide an update on when this will be finished as it severely impacts my daily commute. Thank you. Eric on Twitter Share I was told by Harris County Precinct 4 that the road construction on Park Row between Eldridge and Highway 6 is a Houston Public Works project and so I'm reaching out to you. Park Row has had traffic cones blocking lanes of traffic for over a year and it appears as though all construction is finished many months ago. Can you please provide an update on when this will be finished as it severely impacts my daily commute. Thank you. Eric on Linkedin Email I was told by Harris County Precinct 4 that the road construction on Park Row between Eldridge and Highway 6 is a Houston Public Works project and so I'm reaching out to you. Park Row has had traffic cones blocking lanes of traffic for over a year and it appears as though all construction is finished many months ago. Can you please provide an update on when this will be finished as it severely impacts my daily commute. Thank you. Eric link

    I was told by Harris County Precinct 4 that the road construction on Park Row between Eldridge and Highway 6 is a Houston Public Works project and so I'm reaching out to you. Park Row has had traffic cones blocking lanes of traffic for over a year and it appears as though all construction is finished many months ago. Can you please provide an update on when this will be finished as it severely impacts my daily commute. Thank you. Eric

    egroves1111 asked 3 months ago

    Ready...Set...ENGAGE!

     

    We understand that construction can sometimes disrupt daily life, and we genuinely appreciate your patience as we work to enhance our infrastructure. We’ve recently updated the Park Ten Project page with the latest progress and key details:

     

    1. Park Row Tunneling: We’re gearing up to start tunneling work on Park Row. While this work happens underground and may not be visible, rest assured that significant strides are being made behind the scenes.
    2. Eldridge and Memorial: We’re closely collaborating with our engineers to minimize traffic disruptions during the upcoming construction on Eldridge near Memorial. Our goal is to ensure your daily commute remains as smooth as possible.
    3. N. Eldridge: Construction is also underway at the N. Eldridge Lift Station, located next to the library.

     

    We recognize that the pace or visibility of this work might raise some concerns. Please know that we’re committed to completing these projects efficiently. Much of the work involves tunneling, so crews may not always be visible, but progress is ongoing.  We encourage you to visit the project page: https://www.engagehouston.org/parkten  and subscribe to receive the latest updates via email. Your involvement and support are invaluable, and we want to ensure you’re always in the loop.

     

    Thank you for staying connected with us!

     

  • Share Is there an updated estimation of completion date for the work on Bering Drive between San Felipe and Westheimer? It has been multiple years and the last update I've seen said it would be completed by the end of 2023. Any updates or plans for the project would be helpful! on Facebook Share Is there an updated estimation of completion date for the work on Bering Drive between San Felipe and Westheimer? It has been multiple years and the last update I've seen said it would be completed by the end of 2023. Any updates or plans for the project would be helpful! on Twitter Share Is there an updated estimation of completion date for the work on Bering Drive between San Felipe and Westheimer? It has been multiple years and the last update I've seen said it would be completed by the end of 2023. Any updates or plans for the project would be helpful! on Linkedin Email Is there an updated estimation of completion date for the work on Bering Drive between San Felipe and Westheimer? It has been multiple years and the last update I've seen said it would be completed by the end of 2023. Any updates or plans for the project would be helpful! link

    Is there an updated estimation of completion date for the work on Bering Drive between San Felipe and Westheimer? It has been multiple years and the last update I've seen said it would be completed by the end of 2023. Any updates or plans for the project would be helpful!

    SM1121htx asked 5 months ago

    Ready...Set...ENGAGE!

    The completion of this project is anticipated to be the end of June 2024, weather permitting.

  • Share Why are there no speed limit signs and/or stop signs on Northline Dtive between Little York and Canino? This is a four line section in a residential area where one speeding car already crashed into a reaidence at 102 East Tomlin Drive. Vehicles speed all day long-.. This is a public safety matter! on Facebook Share Why are there no speed limit signs and/or stop signs on Northline Dtive between Little York and Canino? This is a four line section in a residential area where one speeding car already crashed into a reaidence at 102 East Tomlin Drive. Vehicles speed all day long-.. This is a public safety matter! on Twitter Share Why are there no speed limit signs and/or stop signs on Northline Dtive between Little York and Canino? This is a four line section in a residential area where one speeding car already crashed into a reaidence at 102 East Tomlin Drive. Vehicles speed all day long-.. This is a public safety matter! on Linkedin Email Why are there no speed limit signs and/or stop signs on Northline Dtive between Little York and Canino? This is a four line section in a residential area where one speeding car already crashed into a reaidence at 102 East Tomlin Drive. Vehicles speed all day long-.. This is a public safety matter! link

    Why are there no speed limit signs and/or stop signs on Northline Dtive between Little York and Canino? This is a four line section in a residential area where one speeding car already crashed into a reaidence at 102 East Tomlin Drive. Vehicles speed all day long-.. This is a public safety matter!

    EHPcap1 asked 12 months ago
    Howdy Neighbor!

    Thank you for reaching out to us at Engagehouston.org. We kindly request that you contact 311 to formally submit your concern, as they have the necessary resources and expertise to address your issue more efficiently. Please let us know if you have any further questions or concerns.
  • Share When will the work be done on on bering between san flippe and westheimer? It has been 2 yrs or more. We only keep seeing them digging up the same hole over and over again. The street is caving in and cars are having to dodge potholes. on Facebook Share When will the work be done on on bering between san flippe and westheimer? It has been 2 yrs or more. We only keep seeing them digging up the same hole over and over again. The street is caving in and cars are having to dodge potholes. on Twitter Share When will the work be done on on bering between san flippe and westheimer? It has been 2 yrs or more. We only keep seeing them digging up the same hole over and over again. The street is caving in and cars are having to dodge potholes. on Linkedin Email When will the work be done on on bering between san flippe and westheimer? It has been 2 yrs or more. We only keep seeing them digging up the same hole over and over again. The street is caving in and cars are having to dodge potholes. link

    When will the work be done on on bering between san flippe and westheimer? It has been 2 yrs or more. We only keep seeing them digging up the same hole over and over again. The street is caving in and cars are having to dodge potholes.

    Lgssobel asked about 1 year ago

    Howdy Neighbor!

    The Contractor initially completed the work on Bering Drive. However, the City found several areas for improvement in the new sanitary line. The Contractor had to re-excavate the road to address the deficiencies. At this time, the substantial completion deadline is set for the end of 2023.

  • Share What is going on with the section of Bering drive between San Felipe and Woodway?. This week they moved in and they started scraping/milling off the top layer of the street and a neighbor called 311 and was told it was for sewer line replacement. It was my understanding and listed on this site that the sewer line replacement/ lift station abandonment project just involved the portion of Bering between San Felipe and westheimer and scheduled to be completed summer of 2023. on Facebook Share What is going on with the section of Bering drive between San Felipe and Woodway?. This week they moved in and they started scraping/milling off the top layer of the street and a neighbor called 311 and was told it was for sewer line replacement. It was my understanding and listed on this site that the sewer line replacement/ lift station abandonment project just involved the portion of Bering between San Felipe and westheimer and scheduled to be completed summer of 2023. on Twitter Share What is going on with the section of Bering drive between San Felipe and Woodway?. This week they moved in and they started scraping/milling off the top layer of the street and a neighbor called 311 and was told it was for sewer line replacement. It was my understanding and listed on this site that the sewer line replacement/ lift station abandonment project just involved the portion of Bering between San Felipe and westheimer and scheduled to be completed summer of 2023. on Linkedin Email What is going on with the section of Bering drive between San Felipe and Woodway?. This week they moved in and they started scraping/milling off the top layer of the street and a neighbor called 311 and was told it was for sewer line replacement. It was my understanding and listed on this site that the sewer line replacement/ lift station abandonment project just involved the portion of Bering between San Felipe and westheimer and scheduled to be completed summer of 2023. link

    What is going on with the section of Bering drive between San Felipe and Woodway?. This week they moved in and they started scraping/milling off the top layer of the street and a neighbor called 311 and was told it was for sewer line replacement. It was my understanding and listed on this site that the sewer line replacement/ lift station abandonment project just involved the portion of Bering between San Felipe and westheimer and scheduled to be completed summer of 2023.

    Keshou asked about 1 year ago

    Howdy Neighbor! The area of Bering Drive between San Felipe and Woodway is a part of the Mayor's Street Rehabilitation. The roads are being paved, and the work is not associated with a sewer project. In regards to additional information, please contact 311. Thank You for visiting EngageHouston.org

  • Share When is the Fondren Rd project going to start. It has been in the TBD stage for quite some time. The street is worsening and there has been a lot of damage to vehicles. on Facebook Share When is the Fondren Rd project going to start. It has been in the TBD stage for quite some time. The street is worsening and there has been a lot of damage to vehicles. on Twitter Share When is the Fondren Rd project going to start. It has been in the TBD stage for quite some time. The street is worsening and there has been a lot of damage to vehicles. on Linkedin Email When is the Fondren Rd project going to start. It has been in the TBD stage for quite some time. The street is worsening and there has been a lot of damage to vehicles. link

    When is the Fondren Rd project going to start. It has been in the TBD stage for quite some time. The street is worsening and there has been a lot of damage to vehicles.

    Dre asked over 1 year ago

    Howdy Neighbor! Thank You for contacting Engage Houston regarding your question. We deeply apologize for the delay regarding the Fondren Road Paving and Drainage From Braeswood to Creekbend and Creekbend to W. Airport. We understand the importance of this project for the area. The project is still undergoing design. Our team hears your concerns and is working towards a resolution. In regards to what can be done now, please report the areas that are problematic to 311. The 311 team will be able to direct your concern to the street and traffic team. Once received, the area of concern can be reviewed for repairs. Thank You for visiting EngageHouston.org  

  • Share What is Houston Public Works involvement with the "safe streets" program? W Clay (between Dunlavy and Woodhead) has been designated as a “safe street”. Please confirm when construction will begin on this segment. There are no sidewalks on this part of W Clay and it is very dangerous for pedestrians trying to get to Krogers. Thanks. on Facebook Share What is Houston Public Works involvement with the "safe streets" program? W Clay (between Dunlavy and Woodhead) has been designated as a “safe street”. Please confirm when construction will begin on this segment. There are no sidewalks on this part of W Clay and it is very dangerous for pedestrians trying to get to Krogers. Thanks. on Twitter Share What is Houston Public Works involvement with the "safe streets" program? W Clay (between Dunlavy and Woodhead) has been designated as a “safe street”. Please confirm when construction will begin on this segment. There are no sidewalks on this part of W Clay and it is very dangerous for pedestrians trying to get to Krogers. Thanks. on Linkedin Email What is Houston Public Works involvement with the "safe streets" program? W Clay (between Dunlavy and Woodhead) has been designated as a “safe street”. Please confirm when construction will begin on this segment. There are no sidewalks on this part of W Clay and it is very dangerous for pedestrians trying to get to Krogers. Thanks. link

    What is Houston Public Works involvement with the "safe streets" program? W Clay (between Dunlavy and Woodhead) has been designated as a “safe street”. Please confirm when construction will begin on this segment. There are no sidewalks on this part of W Clay and it is very dangerous for pedestrians trying to get to Krogers. Thanks.

    Greg P asked about 2 years ago

    Howdy  Neighbor,  please contact 3-1-1 to have your concern routed to the proper City of Houston Department for review. Thank you for your comments and sharing your concern(s)

  • Share We live on W Clay. W Clay between Dunlavy and Woodhead has been designated as a “safe street”. When will construction begin to add sidewalks? There are currently no sidewalks on this sego. Thanks. on Facebook Share We live on W Clay. W Clay between Dunlavy and Woodhead has been designated as a “safe street”. When will construction begin to add sidewalks? There are currently no sidewalks on this sego. Thanks. on Twitter Share We live on W Clay. W Clay between Dunlavy and Woodhead has been designated as a “safe street”. When will construction begin to add sidewalks? There are currently no sidewalks on this sego. Thanks. on Linkedin Email We live on W Clay. W Clay between Dunlavy and Woodhead has been designated as a “safe street”. When will construction begin to add sidewalks? There are currently no sidewalks on this sego. Thanks. link

    We live on W Clay. W Clay between Dunlavy and Woodhead has been designated as a “safe street”. When will construction begin to add sidewalks? There are currently no sidewalks on this sego. Thanks.

    Greg P asked about 2 years ago

    Howdy  Neighbor, We are so very sorry to hear this. Please contact 3-1-1 to have your concern routed to the proper City of Houston Department for review. Thank you for your comments and sharing your concern(s)


  • Share Are there any plans to inprove Campbell road between Long Point and Blalock? Lots of potholes, no sidewalks for majority of road and people speed along that part of the road. on Facebook Share Are there any plans to inprove Campbell road between Long Point and Blalock? Lots of potholes, no sidewalks for majority of road and people speed along that part of the road. on Twitter Share Are there any plans to inprove Campbell road between Long Point and Blalock? Lots of potholes, no sidewalks for majority of road and people speed along that part of the road. on Linkedin Email Are there any plans to inprove Campbell road between Long Point and Blalock? Lots of potholes, no sidewalks for majority of road and people speed along that part of the road. link

    Are there any plans to inprove Campbell road between Long Point and Blalock? Lots of potholes, no sidewalks for majority of road and people speed along that part of the road.

    Jennburb asked over 2 years ago

    Thank you for contacting Engagehouston.org. As of right now, there are no plans for improvements on Campbell road between Long Point and Blalock. Thank you.

  • Share Can anyone tell me when the bridge project on Botany Ln and Leitrim is scheduled for completion? on Facebook Share Can anyone tell me when the bridge project on Botany Ln and Leitrim is scheduled for completion? on Twitter Share Can anyone tell me when the bridge project on Botany Ln and Leitrim is scheduled for completion? on Linkedin Email Can anyone tell me when the bridge project on Botany Ln and Leitrim is scheduled for completion? link

    Can anyone tell me when the bridge project on Botany Ln and Leitrim is scheduled for completion?

    sdcwatson asked almost 3 years ago

    Thank you for your question. The project is scheduled to be completed in October of 2022.