Kirkwood Road - Subproject 2

Share Kirkwood Road - Subproject 2 on Facebook Share Kirkwood Road - Subproject 2 on Twitter Share Kirkwood Road - Subproject 2 on Linkedin Email Kirkwood Road - Subproject 2 link

PROJECT NUMBER N-100029-0002

LOCATION Refer to map

COUNCIL DISTRICT G

BUDGET $25,410,000

TYPE Street

START Summer 2023

COMPLETION Fall 2025

DETAILS The work includes new concrete and asphalt pavement, curbs, wheelchair ramps, sidewalks, streetlights, and reconstruction of median openings. The existing drainage system will be upgraded with the installation of new stormwater, inlets, manholes, and inline detention. The existing water main will be replaced to include new fire hydrants and valves.


MAP

Project Map


General Project Information

What is the purpose of this project?

This project is a part of the Street and Traffic Capital Improvement project and is necessary to improve roadway and traffic mobility and to meet City of Houston Design Standards.


Have More Questions? Click here for more answers.

PROJECT NUMBER N-100029-0002

LOCATION Refer to map

COUNCIL DISTRICT G

BUDGET $25,410,000

TYPE Street

START Summer 2023

COMPLETION Fall 2025

DETAILS The work includes new concrete and asphalt pavement, curbs, wheelchair ramps, sidewalks, streetlights, and reconstruction of median openings. The existing drainage system will be upgraded with the installation of new stormwater, inlets, manholes, and inline detention. The existing water main will be replaced to include new fire hydrants and valves.


MAP

Project Map


General Project Information

What is the purpose of this project?

This project is a part of the Street and Traffic Capital Improvement project and is necessary to improve roadway and traffic mobility and to meet City of Houston Design Standards.


Have More Questions? Click here for more answers.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    We’re pleased to share the latest developments:


    Current Progress:

    • The storm system is now complete on the east side of Kirkwood, from Briar Forest to Overbrook.
    • Water and wastewater infrastructure installations are fully completed.
    • Paving on the east side of Kirkwood from Briar Forest to Overbrook is finished.

    Next Steps:

    • Storm system installation on the west side of Kirkwood is underway.
    • Pavement removal has started on the southbound lanes, with traffic now open on the newly completed pavement north of Waldemar.


    Thank you for your continued support. We’ll keep you updated as we progress with the project.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    We’re excited to share the latest progress on the Kirkwood Road - Subproject 2:


    • Detention system: Installation is currently underway.
    • Water and wastewater work: This phase is complete.
    • Paving: The east side of Kirkwood, from Briar Forest to Southlake, has been successfully paved.


    We appreciate your support and will continue to keep you updated as the project advances.


  • Traffic Control Update

    Share Traffic Control Update on Facebook Share Traffic Control Update on Twitter Share Traffic Control Update on Linkedin Email Traffic Control Update link

    WHAT

    Traffic Lane Changes from Briar Forest to Waldemar and from Waldemar to Westheimer.

    WHEN

    September 5th, 2024 - To Be Determined

    WHY

    Stormwater System Installation and Paving

    UPDATE There will be a shift in construction to the Southbound side of Kirkwood starting next week. Residents will now be driving on the new pavement (North Bound lanes) from Briar Forest to Waldemar then would shift back to the Southside from Waldemar to Westheimer. Stormwater on the Northbound side continues and is complete up to Southlake. With the closure of a portion of the Southbound side stormwater installation will be occurring simultaneously on both sides. Pavement on the Northbound side is also complete up to Poplar Creek and the contractor works continues.

    WHO TO CONTACT

    Houston 311 reference Project Number N-100029-0002


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    We want to provide an update on the progress of the Kirkwood Road - Subproject 2. As of Summer 2024, here is a summary of our progress:


    Progress Update:

    • Waterlines and wastewater lines: work expected to be complete by Summer 2024.
    • Stormwater System: Installation is finished from Briar Forest to Southlake on the Northbound side of Kirkwood.
    • Paving and Shared-Use Path: Paving is complete from Briar Forest to Waldemar, and portions of the 10-foot shared-use path is complete on the Northbound side of Kirkwood.

    Next Steps:

    • The contractor will continue with stormwater installation and paving on the Northbound side before starting on the Southbound side. Look for the traffic control changes once the Southbound Consruction starts.


    We appreciate your continued support and understanding. The project remains on schedule for completion in Fall 2025.


    Thank you!

  • Water Outage Reminder

    Share Water Outage Reminder on Facebook Share Water Outage Reminder on Twitter Share Water Outage Reminder on Linkedin Email Water Outage Reminder link

    All businesses and homeowners who are projected to be out of water was notified by the Contractor on June 24th.


    WHAT

    Water Disruption

    WHERE

    Kirkwood from Westheimer to Southlake and along Westheimer (north side) from Grey Falls to Kirkwood. Small portion of the subdivision between Southlake and Waldemar.

    WHEN

    June 27th @ 6:30PM for 8-10 hours

    WHY

    To preform wet connections to the water line.

    WHO TO CONTACT

    Houston 311 reference Project # N-100029-0002


  • Water Service Outage

    Share Water Service Outage on Facebook Share Water Service Outage on Twitter Share Water Service Outage on Linkedin Email Water Service Outage link

    An emergency repair is planned for this evening along Kirkwood between Overbrook and Southlake. It will likely shut off water in the area between these streets for at least 6-8 hours.


    WHAT

    Water Line Break

    WHERE

    Along Kirkwood

    WHEN

    June 25th

    WHY

    A break in the existing 16-inch water line

    WHO TO CONTACT

    Houston 311 reference Project # N-100029-0002


  • Traffic Update

    Share Traffic Update on Facebook Share Traffic Update on Twitter Share Traffic Update on Linkedin Email Traffic Update link

    We are performing construction near Waldemar and Kirkwood crossing, our contractor has ensured that during peak hours, morning and afternoon, flaggers will be available to help get pedestrian traffic safely across. The flaggers will again be implemented by the contractor during the paving operations at this intersection. In addition, contractors will have additional barrels and traffic control devices in place during this construction.


  • Water Service Outage

    Share Water Service Outage on Facebook Share Water Service Outage on Twitter Share Water Service Outage on Linkedin Email Water Service Outage link

    Residents affected along Kirkwood from just south of Briar Forest to just north of Southlake Dr. and those residents along Waldemar from Cherry Bend to Kirkwood.


    WHAT

    Water Service Outage

    WHEN

    Friday March 1st from 7AM to 3PM

    WHY

    To tie in the new waterline

    WHO TO CONTACT

    Houston 311 reference project number N-100029-0002

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The waterline has been repaired, and all services have been restored.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    A water main break was reported on February 8th. The contractor is currently addressing the issue with urgency and diligence. Further updates will be provided as soon as they are available. Thank you for your patience and understanding.