Completed to Date:
- The contractor has completed the wastewater system improvements and continues to install the proposed wastewater system along the project alignment.
- The contractor has commenced the installation of the 16-inch water line proposed along Kirkwood. Approximately 300 linear feet of the 3500 linear feet have been installed.
Planned Work (Next 30 Days)
- Continue installation of the wastewater system.
- Continue installation of 16-inch water line. Start testing the water line.
- The contractor anticipates the water and wastewater work will be completed in April.