Completed to Date:

  • Contractor has completed the wastewater system improvements. Contractor continues to install the proposed wastewater system along the project alignment.
  • Contractor has commenced the installation of the 16-inch water line proposed along Kirkwood. Approximately 300 linear feet of the 3500 linear feet has been installed to date.

Planned Work (Next 30 Days)

  • Continue installation of wastewater system.
  • Continue installation of 16-inch water line. Start testing the water line.
  • Contractor anticipates the water and wastewater work will be completed in April.