Fountain View Regional Lift Station

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER R-000536-0023

LOCATION Fountain View between Westheimer Rd. and Gulfton St.

COUNCIL DISTRICTG, I

BUDGET $25,506,517

TYPE Wastewater

START Spring 2020

COMPLETION Winter 2022

DETAILS The project provides for the abandonment of the old lift station near Fountain View and Westheimer and connecting to a new lift station near Fountain View and US 59.


MAP

project map



What is the purpose of this project?
This project provides for the implementation of a plan for the phased consolidation of facilities.

How long is this project going to take to complete?
22 months (630 calendar days). Work begins Monday, May 4, 2020, and the completion date is projected for Tuesday, December 20, 2022. These dates are estimates. The project schedule depends upon weather conditions and the contractor's production rate.


Have More Questions? Click here for more answers

PROJECT NUMBER R-000536-0023

LOCATION Fountain View between Westheimer Rd. and Gulfton St.

COUNCIL DISTRICTG, I

BUDGET $25,506,517

TYPE Wastewater

START Spring 2020

COMPLETION Winter 2022

DETAILS The project provides for the abandonment of the old lift station near Fountain View and Westheimer and connecting to a new lift station near Fountain View and US 59.


MAP

project map



What is the purpose of this project?
This project provides for the implementation of a plan for the phased consolidation of facilities.

How long is this project going to take to complete?
22 months (630 calendar days). Work begins Monday, May 4, 2020, and the completion date is projected for Tuesday, December 20, 2022. These dates are estimates. The project schedule depends upon weather conditions and the contractor's production rate.