Forest Shores and Woodland Ridge Lift Stations

Share Forest Shores and Woodland Ridge Lift Stations on Facebook Share Forest Shores and Woodland Ridge Lift Stations on Twitter Share Forest Shores and Woodland Ridge Lift Stations on Linkedin Email Forest Shores and Woodland Ridge Lift Stations link

PROJECT NUMBER R-000035-006A/B

LOCATION Kingwood Dr. between Woodland Hills and Forest Shores

COUNCIL DISTRICT E

BUDGET $11,337,434

TYPE Wastewater

START Spring 2020

COMPLETION Winter 2022

DETAILS The project provides for the renewal and replacement of wastewater force mains and is necessary due to the age and condition of force mains.


MAPproject map



What is the purpose of this project?
This project provides for the renewal and replacement of wastewater force mains and is necessary due to the age and conditions of the force mains.

How long is this project going to take to complete?
Woodland Ridge Lift Station: Work is scheduled to begin on May 11, 2020, and will last approximately 80days.
Forest Shores Lift Station: Work is scheduled to begin on June 22, 2020, and will last approximately 64 days.

The project schedule could be impacted by wet weather conditions


Have More Questions? Click here for more answers




PROJECT NUMBER R-000035-006A/B

LOCATION Kingwood Dr. between Woodland Hills and Forest Shores

COUNCIL DISTRICT E

BUDGET $11,337,434

TYPE Wastewater

START Spring 2020

COMPLETION Winter 2022

DETAILS The project provides for the renewal and replacement of wastewater force mains and is necessary due to the age and condition of force mains.


MAPproject map



What is the purpose of this project?
This project provides for the renewal and replacement of wastewater force mains and is necessary due to the age and conditions of the force mains.

How long is this project going to take to complete?
Woodland Ridge Lift Station: Work is scheduled to begin on May 11, 2020, and will last approximately 80days.
Forest Shores Lift Station: Work is scheduled to begin on June 22, 2020, and will last approximately 64 days.

The project schedule could be impacted by wet weather conditions


Have More Questions? Click here for more answers