Fuqua Street between Blackhawk Boulevard and Monroe Road has been reduced from four lanes to two lanes to allow construction work to continue.
WHEN
Now through Fall 2026
WHY
This lane reduction is needed to safely support upcoming tunneling work and keep the project moving on schedule.
UPDATE
As part of the Easthaven to Southeast Wastewater Treatment Plant – Package 2 project, contractors will begin tunneling operations in the coming weeks—an important milestone that keeps the overall effort on track for completion in Spring 2027. Traffic control will remain in place while work progresses.
WHO TO CONTACT
Houston 311 and reference Project Number R-000536-034A.