Southeast Wastewater Treatment Plant Improvements / Expansion - Package 1

Share Southeast Wastewater Treatment Plant Improvements / Expansion - Package 1 on Facebook Share Southeast Wastewater Treatment Plant Improvements / Expansion - Package 1 on Twitter Share Southeast Wastewater Treatment Plant Improvements / Expansion - Package 1 on Linkedin Email Southeast Wastewater Treatment Plant Improvements / Expansion - Package 1 link

PROJECT NUMBER R-000265-0126

LOCATION Refer to project map

COUNCIL DISTRICT D

BUDGET $50,669,425

TYPE Wastewater

START Winter 2023

COMPLETION Spring 2025

DETAILS This project provides for the design and construction of electrical, mechanical, structure, process, and piping improvements at various wastewater treatment facilities throughout the City.


MAP

Project Map



General Project Information

What is the purpose of this project?
This project is part of the City's on-going program for improvements and expansion to the major wastewater treatments plants.


How long is this project going to take to complete?
27 months (820 calendar days). Work is scheduled to begin in Winter 2023 and is anticipated to be completed in Spring 2025. The project schedule depends upon weather conditions. Please see the phasing map for details.


Have More Questions? Click here for more answers

PROJECT NUMBER R-000265-0126

LOCATION Refer to project map

COUNCIL DISTRICT D

BUDGET $50,669,425

TYPE Wastewater

START Winter 2023

COMPLETION Spring 2025

DETAILS This project provides for the design and construction of electrical, mechanical, structure, process, and piping improvements at various wastewater treatment facilities throughout the City.


MAP

Project Map



General Project Information

What is the purpose of this project?
This project is part of the City's on-going program for improvements and expansion to the major wastewater treatments plants.


How long is this project going to take to complete?
27 months (820 calendar days). Work is scheduled to begin in Winter 2023 and is anticipated to be completed in Spring 2025. The project schedule depends upon weather conditions. Please see the phasing map for details.