Lift Station Diversion for MUD #237 and MUD #159

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER R-000267-117B

LOCATION Refer to Project Map

COUNCIL DISTRICT A

BUDGET $7,112,529

TYPE Wastewater

START Summer 2022

COMPLETION To Be Determined

DETAILS The project provides for the Diversion and Demolition of two (2) Wastewater Lift Stations (District 159 and District 237) by installation of approximately 3,300 linear feet of 8-inch to 15-inch diameter gravity sanitary sewer by micro tunnel construction.


MAPProject Map



General Project Information

What is the purpose of this project?

This project is part of the City's Lift Station Renewal and Replacement Improvements program and is required to replace/upgrade lift station facilities. The work to be performed under this contract award is necessary to maintain compliance with Houston's wastewater consent decree with EPA and TCEQ. It is necessary due to the age and condition.


How long is this project going to take to complete?
12 months (365 calendar days). Work is scheduled to begin in Summer 2022 and is anticipated to be completed in Fall 2023. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

PROJECT NUMBER R-000267-117B

LOCATION Refer to Project Map

COUNCIL DISTRICT A

BUDGET $7,112,529

TYPE Wastewater

START Summer 2022

COMPLETION To Be Determined

DETAILS The project provides for the Diversion and Demolition of two (2) Wastewater Lift Stations (District 159 and District 237) by installation of approximately 3,300 linear feet of 8-inch to 15-inch diameter gravity sanitary sewer by micro tunnel construction.


MAPProject Map



General Project Information

What is the purpose of this project?

This project is part of the City's Lift Station Renewal and Replacement Improvements program and is required to replace/upgrade lift station facilities. The work to be performed under this contract award is necessary to maintain compliance with Houston's wastewater consent decree with EPA and TCEQ. It is necessary due to the age and condition.


How long is this project going to take to complete?
12 months (365 calendar days). Work is scheduled to begin in Summer 2022 and is anticipated to be completed in Fall 2023. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

  • January 2023 Updates

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Currently relocations of AT&T Fiber Optics process in ongoing.