Easthaven to Southeast Wastewater Treatment Plant - Package 2

Share Easthaven to Southeast Wastewater Treatment Plant - Package 2 on Facebook Share Easthaven to Southeast Wastewater Treatment Plant - Package 2 on X (formerly Twitter) Share Easthaven to Southeast Wastewater Treatment Plant - Package 2 on Linkedin Email Easthaven to Southeast Wastewater Treatment Plant - Package 2 link

Project Overview

Council District: I

Project Number: R-000536-034A

Estimated Budget: $39,735,000

Start: Spring 2025

Completion: Summer 2027




Project Impact Area

Project Map


Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

Project Overview

Council District: I

Project Number: R-000536-034A

Estimated Budget: $39,735,000

Start: Spring 2025

Completion: Summer 2027




Project Impact Area

Project Map


Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

  • Latest News

    Share Latest News on Facebook Share Latest News on X (formerly Twitter) Share Latest News on Linkedin Email Latest News link

    The project is progressing well! Contractors are actively constructing shafts along Fuqua Street between Blackhawk Boulevard and Monroe Road and installing new wastewater lines.

    To accommodate construction activities, traffic on Fuqua Street between Blackhawk Boulevard and Monroe Road has been reduced from four lanes to two lanes in each direction. Traffic on Monroe Road between Fuqua Street and Swiftwater Street has also been reduced from four lanes to two lanes. We are pleased to report that the project remains on schedule for completion in Summer 2027.

    The project is progressing well! Contractors are actively constructing shafts along Fuqua Street between Blackhawk Boulevard and Monroe Road and installing new wastewater lines.

    To accommodate construction activities, traffic on Fuqua Street between Blackhawk Boulevard and Monroe Road has been reduced from four lanes to two lanes in each direction. Traffic on Monroe Road between Fuqua Street and Swiftwater Street has also been reduced from four lanes to two lanes. We are pleased to report that the project remains on schedule for completion in Summer 2027.

  • Latest News

    Share Latest News on Facebook Share Latest News on X (formerly Twitter) Share Latest News on Linkedin Email Latest News link

    The project is progressing well! Tunneling for the wastewater line along Fuqua Street from Blackhawk Boulevard to Monroe Road will begin soon. The project remains on schedule for completion by Summer 2027.

    The project is progressing well! Tunneling for the wastewater line along Fuqua Street from Blackhawk Boulevard to Monroe Road will begin soon. The project remains on schedule for completion by Summer 2027.

  • Latest News

    Share Latest News on Facebook Share Latest News on X (formerly Twitter) Share Latest News on Linkedin Email Latest News link

    The project is progressing well! Tunnel shaft construction is underway along Fuqua Street from Blackhawk Boulevard to Monroe Road. Next, contractors will begin tunneling wastewater lines along this corridor. The project remains on schedule for completion by Summer 2027.

    The project is progressing well! Tunnel shaft construction is underway along Fuqua Street from Blackhawk Boulevard to Monroe Road. Next, contractors will begin tunneling wastewater lines along this corridor. The project remains on schedule for completion by Summer 2027.

  • Latest News

    Share Latest News on Facebook Share Latest News on X (formerly Twitter) Share Latest News on Linkedin Email Latest News link

    The project is progressing well! Contractors are constructing tunnel shafts along Fuqua Street from Blackhawk Boulevard to Monroe Road. Next, crews will begin tunneling wastewater lines beneath Fuqua Street within the same corridor. We’re pleased to report that the project remains on schedule for completion by Summer 2027.


    The project is progressing well! Contractors are constructing tunnel shafts along Fuqua Street from Blackhawk Boulevard to Monroe Road. Next, crews will begin tunneling wastewater lines beneath Fuqua Street within the same corridor. We’re pleased to report that the project remains on schedule for completion by Summer 2027.


Page last updated: 15 Jun 2026, 09:49 AM