Chelford City Diversion Package 3

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER R-000536-0029

LOCATION Refer to project map

COUNCIL DISTRICT F

BUDGET $17,310,659

TYPE Wastewater

START Fall 2022

COMPLETION To Be Determined

DETAILS The project provides for the implementation of a plan for the phased consolidation of facilities.


MAPProject Map


General Project Information

What is the purpose of this project?
The purpose of the project is to construct a new gravity sewer to decommission the Green Crest Lift Station and divert the flow to the Upper Brays Wastewater Treatment Plant.

How long is this project going to take to complete?

The project schedule was placed on hold, please see updates below for further information.

The City will post a new schedule once available.



PROJECT NUMBER R-000536-0029

LOCATION Refer to project map

COUNCIL DISTRICT F

BUDGET $17,310,659

TYPE Wastewater

START Fall 2022

COMPLETION To Be Determined

DETAILS The project provides for the implementation of a plan for the phased consolidation of facilities.


MAPProject Map


General Project Information

What is the purpose of this project?
The purpose of the project is to construct a new gravity sewer to decommission the Green Crest Lift Station and divert the flow to the Upper Brays Wastewater Treatment Plant.

How long is this project going to take to complete?

The project schedule was placed on hold, please see updates below for further information.

The City will post a new schedule once available.



  • Latest News

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The City is collaborating with the Surety company to restart construction. The Surety is currently selecting a qualified contractor from received bids.

    We expect the final selection soon. Once chosen, the new contractor will resume construction, and we'll provide a detailed project timeline in advance.

    Ensuring public safety is our main focus. We're keeping essential safety measures, like securing open shafts and maintaining traffic controls, until the work is finished.

  • Latest News

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    BRH Garver, the contractor for the reference project, declared bankruptcy and the City subsequently terminated their contract. Therefore, all construction activity has been suspended on the project. The City is currently evaluating options to find replacement contractors and will provide updates when available. We expect this process to take several months but don’t currently have a definitive timeline.

    For now, the City is simply maintaining critical public safety items such as protecting open shafts and keeping the traffic control devices in place. We apologize for the inconvenience, and we are working as fast as we can to resolve this matter. Thank you.