Chelford City Diversion Package 2

Share Chelford City Diversion Package 2 on Facebook Share Chelford City Diversion Package 2 on Twitter Share Chelford City Diversion Package 2 on Linkedin Email Chelford City Diversion Package 2 link

PROJECT NUMBER R-000536-0027-4

LOCATION Refer to Project Map

COUNCIL DISTRICT F

BUDGET $21,084,000

TYPE Wastewater

START Summer 2022

COMPLETION To Be Determined

DETAILS The project provides for the rehabilitation of six wastewater lift stations. The rehabilitation includes site work and improvements to various equipment.


MAP

Project Map



General Project Information

What is the purpose of this project?
This project is part of the City’s Capital Improvement Plan (CIP) Consolidation Package for wastewater facilities.

How long is this project going to take to complete?

The project schedule was placed on hold, please see updates below for further information.

The City will post a new schedule once available.




PROJECT NUMBER R-000536-0027-4

LOCATION Refer to Project Map

COUNCIL DISTRICT F

BUDGET $21,084,000

TYPE Wastewater

START Summer 2022

COMPLETION To Be Determined

DETAILS The project provides for the rehabilitation of six wastewater lift stations. The rehabilitation includes site work and improvements to various equipment.


MAP

Project Map



General Project Information

What is the purpose of this project?
This project is part of the City’s Capital Improvement Plan (CIP) Consolidation Package for wastewater facilities.

How long is this project going to take to complete?

The project schedule was placed on hold, please see updates below for further information.

The City will post a new schedule once available.




  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The city is collaborating with Surety to restart construction. The Surety is currently selecting a qualified contractor from the received bids.

    We expect the final selection soon. Once chosen, the new contractor will resume construction, and we'll provide a detailed project timeline in advance.

    Ensuring public safety is our main focus. We're keeping essential safety measures, like securing open shafts and maintaining traffic controls until the work is finished.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The City is currently working to finalize a contract for resuming the project work. The new contractor, once selected, will start work in the next few months after the contract is awarded. We will provide a definitive schedule at that time.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    BRH Garver, the contractor for the reference project, declared bankruptcy and the City subsequently terminated their contract. Therefore, all construction activity has been suspended on the project. The City is currently evaluating options to find replacement contractors and will provide updates when available. We expect this process to take several months but don’t currently have a definitive timeline.

    For now, the City is simply maintaining critical public safety items such as protecting open shafts and keeping the traffic control devices in place. We apologize for the inconvenience, and we are working as fast as we can to resolve this matter. Thank you.

Page last updated: 06 Mar 2024, 09:01 AM