Almeda Sims Wastewater Treatment Plant Improvements

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER R-000298-0014

LOCATION Refer to Project Map

COUNCIL DISTRICT D

BUDGET $21,210,192

TYPE Wastewater

START Winter 2022

COMPLETION Winter 2024

DETAILS This project consists of the construction and the replacement of electrical, mechanical, structure, process, and piping components in the facility.


MAPProject Map



General Project Information

What is the purpose of this project?

This project is part of the City’s ongoing program to improve inefficient components of the existing wastewater treatment plant facilities.

How long is this project going to take to complete?
23 months (700 calendar days). Work is scheduled to begin in Winter 2022 and is anticipated to be completed in Winter 2024. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers

PROJECT NUMBER R-000298-0014

LOCATION Refer to Project Map

COUNCIL DISTRICT D

BUDGET $21,210,192

TYPE Wastewater

START Winter 2022

COMPLETION Winter 2024

DETAILS This project consists of the construction and the replacement of electrical, mechanical, structure, process, and piping components in the facility.


MAPProject Map



General Project Information

What is the purpose of this project?

This project is part of the City’s ongoing program to improve inefficient components of the existing wastewater treatment plant facilities.

How long is this project going to take to complete?
23 months (700 calendar days). Work is scheduled to begin in Winter 2022 and is anticipated to be completed in Winter 2024. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers

  • April 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The project is currently 40% completed in place, which includes the installation of storm drains. Current construction activities include the installation of the Electrical duct bank and Acoustical panels in the blower building.

  • January 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Contractor is on site installing the 36-inch storm sewer manhole.

Page last updated: 07 Nov 2023, 11:57 AM